ISO7
Cleanroom Class
155m³
Project Size
Modular
Construction Type
Pre-Assembled
Built In Factory
Fat Verified
Factory Test
2 Months
Total Duration
Project Overview
Shanghai Yantai Technology Co., Ltd. provided an export-oriented ISO 7 modular cleanroom solution for GEO (Green Energy), which was installed inside their factory in Europe as an independent clean experimental workspace.
Client GEO is a company focused on the clean energy industry, with core products including lithium batteries and other new energy technologies. As their R&D and quality control requirements continued to grow, the customer required a clean laboratory environment for product testing, sample analysis, and process verification within their existing factory.
The project adopted a modular cleanroom design consisting of three independent modules, enabling:
Project Scope
Factory prefabrication
Overseas transportation
Rapid on-site installation
Independent clean environment control
The entire system was designed to meet ISO 7 cleanroom requirements while also considering international transportation conditions and fast deployment inside an operating factory.
Project Journey & Timeline
Week 1-2

01
Design & Engineering
Duration: 1-2 Week
User Requirement Review
Layout Planning
Cleanroom Classification Confirmation
HVAC & Utility Coordination
3D Structural Design
Manufacturing Drawing Release
Week 3-6

02
Factory Manufacturing & Pre-assembly
Duration: 4 Week
Modular Steel Structure Fabrication
Sandwich Panel Installation
Doors & Windows Installation
HVAC Ductwork Integration
Electrical & Lighting Installation
PLC & Control System Integration
Factory Pre-assembly of Modules
Week 7

03
FAT (Factory Acceptance Test)
Duration: 1 Week
Cleanroom System Inspection
HVAC Functional Testing
Electrical System Verification
PLC Control Logic Testing
Documentation Review
Client FAT Witness (Optional)
Week 8

04
Packaging & International Delivery
Duration: 1 Week
Module Protection & Packaging
Container Loading
Shipping Documentation Preparation
International Transportation Arrangement
Week 9

05
Site Installation & Commissioning
Duration: 1 Week
Module Positioning
Structural Connection
Utility Connection
HVAC Start-up
Functional Verification
Final Handover
Project Gallery
Project Information
|
Parameter |
Specification |
Parameter |
Specification |
|
Project Location |
Czech Republic |
Total Weight |
12.9 Tons |
|
Project Type |
Modular Cleanroom |
Application |
Material Testing Laboratory |
|
Module Quantity |
3 Modules |
Industry |
Industrial & Testing Laboratories |
|
Overall Size |
14270mm(L) × 3200mm(W) × 3400mm(H) |
Delivery Method |
Factory Prefabrication + Overseas On-Site Assembly |
Ready to Start Your Laboratory Project?
Contact us today to dlscuss your requirements. We provide customized solutions for your success.
Quick Inquiry
Appointment Information
Navigation
Navigation
Contact Us
Phone: +86 400 6250 599
Telephone: +8619072311749
E-mail: info@yt-etcolabs.com
WhatsApp: +86 190 7231 1749
Address:Room 1110, Edenburg Mansion, No.139 Hengxi Road, Minhang District, Shanghai, China